Rate analysis for Back filling Work
There are two types of rate analysis, but you are going to study some government rates, we can found many types of back filling work which are depend on various types are as follows
1. Back filling Material
There are many types of back filling materials which are using at various types of sites. In some important projects like Bridges foundations, metro projects foundations are using crush sand for back filling, on railway track there are using 60-90 mm course aggregates, somewhere 10-20 mm course aggregates are using for back filling, for earthen dams there is using soil for back filling, and some projects of roads, embankments of bridges, building foundations, etc. are using murum. In all world there are commonly using murum for back filling.2. onsite material
Commonly back filling work is done after excavation work, so therefore lot of excavated material is stock at site, and lot of times to avoid extra cost to buy outside material there are using excavated material to back filling, this method is very commonly using in all over world but sometimes the location of site, type of excavated material, etc. need to buy outside materials.3. outside material
In some projects which are located are near creek, near ocean, near sea, near dam, near river, water land, there are water table is up to 5ft from ground level and lot of black cotton soil is there so in these cases after excavation there need to buy outside back filling materials.4. Distance
When we are going to buy outside material to back filling work there is distance factor is very affected on the rate of the material.5. Manual
Sometimes need back filling work manually due to site condition or site location. Like hilly area, under the building, small building in crowded public place, no roads for machine travel. Etc.6. Machine
Now a days we are using all work is done by machine, back filling work is on of from those, now a days lot of types of mini machines are available which are going every were on site like under the building. On road work there is lot of work is done machines.1. Back filling with site material.
2. Back filling with excavated site material.
1. Back filling with site material.
In given table you can get easily idea about how we can prepare the analysis of back filling work,Know the constants required to desired unit to work. He are we are giving you rate analysis details in Cum only, which are using comely in construction industry but material procurement unit might be different than out rate analysis unit. You need to focus on that. If out rate analysis unit is in Cum, but material procurement unit is Brass, so you need to prepare the rate analysis according to that and conversion of material constant will be according to it.
Sr.
No. | Material/Labour
Name | Unit | Constant | Wastage
% | Constant
with Wastage | Rate | Amount
|
BACK FILLING
WITH SITE MATERIAL | |||||||
MATERIAL | |||||||
1. | Construction Water | Litre | 25 | 5% | 26.50 | 0.08 | 2.10 |
LABOUR | |||||||
1. | Back filling by Machine (Mini Poclain) | Cum | 0.95 | 0% | 0.95 | 60.00 | 57.00 |
2. | Back filling by Manual | Brass | 0.018 | 0% | 0.018 | 350 | 6.30 |
3. | Compaction by vibro roller | Cum | 0.015 | 0% | 0.015 | 2000 | 30.00 |
TOTAL
AMOUNT | 95.40 | ||||||
OVERHEADS | |||||||
Plant & Machinery | 1.5% | 1.43 | |||||
Water & Electricity Charges | 1.5% | 1.43 | |||||
TOTAL
AMOUNT WITH OVERHEADS | 98.20 | ||||||
CONTRACTORS PROFIT | 15% | 14.73 | |||||
TOTAL
AMOUNT WITH PROFIT | 112.93 | ||||||
SAY | 115.00 |
2. Back filling with outside material
As we discussed above as why need outside material, but outside material rate is depend on distance from site. As well as type of material as discussed.But in general there are using a practice as follows
0-10 km: Rs. 0.00/Cum
10-20 Km: Rs. 20.00/Cum
20-30 Km: Rs. 40.00/Cum
30-50 Km: Rs. 60.00/Cum
But lot of times this is depend on quantity of work, if there is huge quantity of work, and then there is no one considering this distance factor.
Sr.
No. | Material/Labour
Name | Unit | Constant | Wastage
% | Constant
with Wastage | Rate | Amount
|
BACK FILLING
WITH SITE MATERIAL | |||||||
MATERIAL | |||||||
1. | Murum | Brass | 0.353 | 10% | 0.3887 | 900 | 349.83 |
2. | Construction Water | Litre | 25 | 5% | 26.25 | 0.08 | 2.10 |
LABOUR | |||||||
1. | Back filling by Machine (Mini Poclain) | Cum | 0.95 | 0% | 0.95 | 60.00 | 57.00 |
2. | Back filling by Manual | Brass | 0.018 | 0% | 0.018 | 350 | 6.30 |
3. | Compaction by vibro roller | Cum | 0.015 | 0% | 0.015 | 2000 | 30.00 |
TOTAL
AMOUNT | 445.23 | ||||||
OVERHEADS | |||||||
Plant & Machinery | 1.5% | 6.678 | |||||
Water & Electricity Charges | 1.5% | 6.678 | |||||
TOTAL
AMOUNT WITH OVERHEADS | 458.58 | ||||||
CONTRACTORS PROFIT | 15% | 68.78 | |||||
TOTAL
AMOUNT WITH PROFIT | 527.37 | ||||||
SAY | 530.00 |
Back filling rate analysis are generally as per given formats but rates are decided are as per quantity of work, if there is huge quantity of work there will be rate are decided as per the quantum of work.
In back filling work Compaction factor also affecting on rates if any clients given to show the proctor test up to 95% then back filling work need to do very carefully. The back filling work wants to do in layers in 300 mm to 600 mm thickness. As well as back filling need to do under observation to avoid the using of boulders or any other hard materials if using murum. As well as while compaction of murum need to spray the water on compacted surface and then again need to do compaction to achieve the 95% proctor test.
2 Comments
This comment has been removed by a blog administrator.
ReplyDeleteThis comment has been removed by a blog administrator.
ReplyDelete