EXCAVATION WORK ANALYSIS OF RATES
Excavation Work
Excavation Work is the first task before starting any construction,
there are many types of excavations like by machinery, by manual, by the breaker, by
tunnel cutter, by blasting, mining, etc. there are lots of types of excavation.
But when we are going to start actual work, we are facing a big question.
WHAT
ABOUT COST?
WHAT
ABOUT RATE?
Now in this the blog we are working on this Question, and it is called a Rate Analysis of Excavation work.
Types of Rate Analysis
- Excavation up to 0.00m to 1.50m Depth
- Excavation up to 1.50m to 3.00m Depth
- Excavation up to 3.00m to 4.50m Depth
- Excavation up to 4.50m to 6.00m Depth
Those are some types of Excavation rate analysis, where we can again distribute this in the following items.
- Excavation in Soft Soil
- Excavations in Soft Murum
- Excavations in Hard Murum
- Excavations in Soft Rock
- Excavations in Hard Rock
- Excavations by Breaker
These are a few sub-tasks of excavation work. Now we will work on all of the items, one by one, and do the actual rate analyses so we can be easily know what is exact rate of excavation and what cost required bidding while tendering.
1.Excavation in Soft Soil.
In this type of Excavation work we need to find out the actual material type of earthwork, it should be soft soil if this is harder and cannot be possible to excavate by manual, or cannot be excavated by machine bucket then should change the rate of work, because it will be the costly than excavation in soft soil. Some of our contractors keep all the record as per the level and excavation depth. They are doing the simple thing 1st excavating soft material by machine Bucket and then take all the reading of excavated level. And then start excavation in hard Murum or hard rock actually this the standard practice and all should follow this, All actual ground levels will help you get the exact quantity of the excavation area, as well as you will put the bill according to it.
Sr. No. |
Item Description |
Quantity |
Unit |
Material/Labour Description |
Constant |
Unit |
Rate |
Amount |
1 |
Excavation in Soft Soil. |
|||||||
|
|
1 |
Cum |
|
|
|
|
|
|
||||||||
|
LABOUR |
Excavation by Machine (Poclain) (By Bucket) |
1.00 |
Cum |
90.00 |
90.00 |
||
Total Labour |
|
|
|
90.00 |
||||
|
||||||||
|
|
TOTAL AMOUNT |
|
|
|
90.00 |
||
|
|
15% Contractor |
|
|
|
13.50 |
||
|
|
TOTAL AMOUNT |
|
|
|
103.50 |
2.Excavation in Soft Soil. (By Bucket)
Earthwork in excavation by mechanical means (Hydraulic excavator) / manual means over areas Up to 1.5 m including Lifting & Shifting on Site.
In this type of work, we should check the strata of the ground, where we can sell this Murum to the other party, but at this time we should check the distance between the to site. If the distance is more than 10km we need to work on the rate.
Excavator With Bucket Output is 30 Cum/Hour
Sr. No. |
Item Description |
Quantity |
Unit |
Material/Labour Description |
Constant |
Unit |
Rate |
Amount |
|
1 |
Excavation in Soft Soil/Murum. (By
Bucket) |
||||||||
|
|
1 |
Cum |
|
|
|
|
|
|
|
MATERIAL |
Hydraulic Excavator (Poclain/JCB/Mini Excavator)
including Operator, Fuel & Machine Maintenance (By Bucket) |
0.0041 |
Day |
8000 |
32.80 |
|||
Hire and running charges of a loader. |
0.0041 |
Day |
5000 |
20.50 |
|||||
Total Material |
|
|
|
53.30 |
|||||
|
|||||||||
|
LABOUR |
Beldar |
0.04 |
Day |
363.00 |
14.52 |
|||
Male Coolie |
0.20 |
Day |
329.00 |
65.80 |
|||||
Total Labour |
|
|
|
80.32 |
|||||
|
|||||||||
|
Total Material & Labour |
|
|
|
|
133.62 |
|||
|
Overheads |
Add 1% Water Charges |
|
|
|
1.34 |
|||
|
|||||||||
|
|
TOTAL AMOUNT |
|
|
|
134.96 |
|||
|
|
15% Contractor |
|
|
|
20.24 |
|||
|
|
TOTAL AMOUNT |
|
|
|
155.20 |
|||
3.Excavation in Soft Murum/Rock.
Earthwork in excavation by Hydraulic excavator above 1.50m & up to 3.00m including material Lifting & Shifting on Site.
Sr. No. |
Item Description |
Quantity |
Unit |
Material/Labour Description |
Constant |
Unit |
Rate |
Amount |
1 |
Excavation in Soft Murum/Rock. |
|||||||
|
|
1 |
Cum |
|
|
|
|
|
|
MATERIAL |
Hydraulic Excavator (Poclain/JCB/Mini Excavator)
including Operator, Fuel & Machine Maintenance |
0.0063 |
Day |
8000 |
50.40 |
||
Hire and running charges of Hywa/Dumper. |
0.0063 |
Day |
1700 |
10.71 |
||||
Total Material |
|
|
|
61.11 |
||||
|
||||||||
|
LABOUR |
Rock Excavator |
0.0705 |
Day |
329.00 |
23.19 |
||
Rock Breaker |
0.159 |
Day |
329.00 |
52.31 |
||||
Rock Hole Driller |
0.0355 |
Day |
329 |
11.67 |
||||
Beldar |
0.05 |
Day |
329 |
16.45 |
||||
Male Helper |
0.135 |
Day |
329 |
44.41 |
||||
Sundries |
1.79 |
LS |
1.78 |
3.19 |
||||
Total Labour |
|
|
|
151.22 |
||||
|
||||||||
|
Total Material & Labour |
|
|
|
|
212.33 |
||
|
Overheads |
Add 1% Water Charges |
|
|
|
2.1233 |
||
|
||||||||
|
|
TOTAL AMOUNT |
|
|
|
214.45 |
||
|
|
15% Contractor |
|
|
|
32.17 |
||
|
|
TOTAL AMOUNT |
|
|
|
246.62 |
4. Excavation in Hard Rock. (BY Breaker)
Excavation work by Hydraulic excavator in foundation, trenches, drains up to 1.5m, including Excavated material shifting on Site
Sr. No. |
Item Description |
Quantity |
Unit |
Material/Labour Description |
Constant |
Unit |
Rate |
Amount |
1 |
Excavation in Hard Rock. (BY
Breaker) |
|||||||
|
|
1 |
Cum |
|
|
|
|
|
|
MATERIAL |
Hydraulic Excavator (Poclain/JCB/Mini Excavator) including
Operator, Fuel & Machine Maintenance (By Breaker) |
0.0063 |
Day |
8000 |
50.40 |
||
Hire and running charges of Hywa /Dumper. |
0.0063 |
Day |
1700 |
10.71 |
||||
Total Material |
|
|
|
61.11 |
||||
|
||||||||
|
LABOUR |
Rock Excavator |
0.0855 |
Day |
329.00 |
28.12 |
||
Rock Breaker |
0.1765 |
Day |
329.00 |
58.06 |
||||
Rock Hole Driller |
0.0530 |
Day |
329.00 |
17.43 |
||||
Beldar |
0.050 |
Day |
329.00 |
16.45 |
||||
Male Helper |
0.130 |
Day |
329.00 |
42.77 |
||||
Sundries |
1.35 |
LS |
1.78 |
2.40 |
||||
Total Labour |
|
|
|
165.23 |
||||
|
||||||||
|
Total Material & Labour |
|
|
|
|
226.34 |
||
|
Overheads |
Add 1% Water Charges |
|
|
|
2.26 |
||
|
||||||||
|
|
TOTAL AMOUNT |
|
|
|
228.60 |
||
|
|
15% Contractor |
|
|
|
34.29 |
||
|
|
TOTAL AMOUNT |
|
|
|
262.89 |
5. Excavation in Hard Rock. (BY Breaker/Blasting)
Excavation work by Hydraulic excavator in foundation, trenches, drains up to 1.5m, including Excavated material shifting on Site.
Sr. No. |
Item Description |
Quantity |
Unit |
Material/Labour Description |
Constant |
Unit |
Rate |
Amount |
1 |
Excavation in Hard Rock. (BY Breaker/Blasting) |
|||||||
|
|
1 |
Cum |
|
|
|
|
|
|
MATERIAL |
Hydraulic Excavator (Poclain/JCB/Mini Excavator) including
Operator, Fuel & Machine Maintenance (By Breaker) |
0.0125 |
Day |
8000 |
100.00 |
||
Hire and running charges of Hywa/Dumper. |
0.0125 |
Day |
1700 |
21.25 |
||||
Total Material |
|
|
|
121.25 |
||||
|
||||||||
|
LABOUR |
Rock Excavator |
0.124 |
Day |
329.00 |
40.79 |
||
Rock Breaker |
0.300 |
Day |
329.00 |
98.70 |
||||
Rock Hole Driller |
0.1060 |
Day |
329.00 |
34.87 |
||||
Beldar |
0.050 |
Day |
329.00 |
16.45 |
||||
Male Helper |
0.130 |
Day |
329.00 |
42.77 |
||||
Blasting Powder |
0.642 |
Kg |
35 |
22.47 |
||||
Blasting Fuse with Wire |
0.7 |
Per Nos |
15 |
10.50 |
||||
Sundries |
1.85 |
LS |
1.78 |
3.35 |
||||
Total Labour |
|
|
|
269.90 |
||||
|
||||||||
|
Total Material & Labour |
|
|
|
|
391.15 |
||
|
Overheads |
Add 1% Water Charges |
|
|
|
3.91 |
||
|
||||||||
|
|
TOTAL AMOUNT |
|
|
|
395.06 |
||
|
|
15% Contractor |
|
|
|
59.25 |
||
|
|
TOTAL AMOUNT |
|
|
|
454.32 |
6. Excavation in Hard Rock. (BY Breaker/Without
Blasting)
Excavation work by Hydraulic excavator up to 1.5m, including Excavated material shifting on Site.
The rate of shifting of material is considered on-site, but if there is no space to spread the excavated material so you need to shift all the excavated material to another place other than the site, the rate of shifting of excavated material depends on the distance between two sites.
Sr. No. |
Item Description |
Quantity |
Unit |
Material/Labour Description |
Constant |
Unit |
Rate |
Amount |
1 |
Excavation in Hard Rock. (BY Breaker/without
Blasting) |
|||||||
|
|
1 |
Cum |
|
|
|
|
|
|
MATERIAL |
Hydraulic Excavator (Poclain/JCB/Mini Excavator)
including Operator, Fuel & Machine Maintenance (By Breaker) |
0.0125 |
Day |
8000 |
100.00 |
||
Hire and running charges of Hywa/Dumper. |
0.0125 |
Day |
1700 |
21.25 |
||||
Total Material |
|
|
|
121.25 |
||||
|
||||||||
|
LABOUR |
Rock Excavator |
0.265 |
Day |
329.00 |
87.185 |
||
Rock Breaker |
0.6175 |
Day |
329.00 |
203.15 |
||||
Stone Chiseller |
0.1060 |
Day |
363.00 |
38.47 |
||||
Blacksmith 2nd Class |
0.0175 |
Day |
399.00 |
6.98 |
||||
Beldar |
0.075 |
Day |
329.00 |
24.675 |
||||
Male Helper |
0.150 |
Day |
329.00 |
49.35 |
||||
Sundries |
1.784 |
LS |
1.78 |
3.175 |
||||
Total Labour |
|
|
|
412.98 |
||||
|
||||||||
|
Total Material & Labour |
|
|
|
|
534.24 |
||
|
Overheads |
Add 1% Water Charges |
|
|
|
5.34 |
||
|
||||||||
|
|
TOTAL AMOUNT |
|
|
|
539.57 |
||
|
|
15% Contractor |
|
|
|
80.93 |
||
|
|
TOTAL AMOUNT |
|
|
|
620.50 |
Team
CBEC India
3 Comments
Are you looking for high-technology excavators for a perfect beginning of your project? You have come over the exact place. From now on, look no further than Australian Demolition & Excavations. We are the top most all in one solution for all your excavation and demolition needs, contact us to trust us and hire excavator in Melbourne from us for your upcoming project.
ReplyDeleteWhat currency are these rates based?
ReplyDeleteIndian Rupees
Delete