EXCAVATION WORK ANALYSIS OF RATES




Excavation Work

Excavation Work is the first task before starting any construction, there are many types of excavations like by machinery, by manual, by the breaker, by tunnel cutter, by blasting, mining, etc. there are lots of types of excavation. But when we are going to start actual work, we are facing a big question.

WHAT ABOUT COST?

WHAT ABOUT RATE?

 

Now in this the blog we are working on this Question, and it is called a Rate Analysis of Excavation work.

 

Types of Rate Analysis

  1. Excavation up to 0.00m to 1.50m Depth
  2. Excavation up to 1.50m to 3.00m Depth
  3. Excavation up to 3.00m to 4.50m Depth
  4. Excavation up to 4.50m to 6.00m Depth

Those are some types of Excavation rate analysis, where we can again distribute this in the following items.

  • Excavation in Soft Soil
  • Excavations in Soft Murum
  •  Excavations in Hard Murum
  • Excavations in Soft Rock
  • Excavations in Hard Rock
  • Excavations by Breaker

These are a few sub-tasks of excavation work. Now we will work on all of the items, one by one, and do the actual rate analyses so we can be easily know what is exact rate of excavation and what cost required bidding while tendering.

1.Excavation in Soft Soil.

In this type of Excavation work we need to find out the actual material type of earthwork, it should be soft soil if this is harder and cannot be possible to excavate by manual, or cannot be excavated by machine bucket then should change the rate of work, because it will be the costly than excavation in soft soil. Some of our contractors keep all the record as per the level and excavation depth. They are doing the simple thing 1st excavating soft material by machine Bucket and then take all the reading of excavated level. And then start excavation in hard Murum or hard rock actually this the standard practice and all should follow this, All actual ground levels will help you get the exact quantity of the excavation area, as well as you will put the bill according to it.

Sr. No.

Item Description

Quantity

Unit

Material/Labour Description

Constant

Unit

Rate

Amount

1

Excavation in Soft Soil.

 

 

1

Cum

 

 

 

 

 

 

 

LABOUR

Excavation by Machine (Poclain) (By Bucket)

1.00

Cum

90.00

90.00

Total Labour

 

 

 

90.00

 

 

 

TOTAL AMOUNT

 

 

 

90.00

 

 

15% Contractor

 

 

 

13.50

 

 

TOTAL AMOUNT

 

 

 

103.50

 

2.Excavation in Soft Soil. (By Bucket)

Earthwork in excavation by mechanical means (Hydraulic excavator) / manual means over areas Up to  1.5 m including Lifting & Shifting on Site.

In this type of work, we should check the strata of the ground, where we can sell this Murum to the other party, but at this time we should check the distance between the to site. If the distance is more than 10km we need to work on the rate.

Excavator With Bucket Output is 30 Cum/Hour

Sr. No.

Item Description

Quantity

Unit

Material/Labour Description

Constant

Unit

Rate

Amount

1

Excavation in Soft Soil/Murum. (By Bucket)

 

 

1

Cum

 

 

 

 

 

 

MATERIAL

Hydraulic Excavator (Poclain/JCB/Mini Excavator) including Operator, Fuel & Machine Maintenance (By Bucket)

0.0041

Day

8000

32.80

Hire and running charges of a loader.

0.0041

Day

5000

20.50

Total Material

 

 

 

53.30

 

 

LABOUR

Beldar

0.04

Day

363.00

14.52

Male Coolie

0.20

Day

329.00

65.80

Total Labour

 

 

 

80.32

 

 

Total Material & Labour

 

 

 

 

133.62

 

Overheads

Add 1% Water Charges

 

 

 

1.34

 

 

 

TOTAL AMOUNT

 

 

 

134.96

 

 

15% Contractor

 

 

 

20.24

 

 

TOTAL AMOUNT

 

 

 

155.20

3.Excavation in Soft Murum/Rock.

Earthwork in excavation by Hydraulic excavator above 1.50m & up to 3.00m including material Lifting & Shifting on Site. 

Sr. No.

Item Description

Quantity

Unit

Material/Labour Description

Constant

Unit

Rate

Amount

1

Excavation in Soft Murum/Rock.

 

 

1

Cum

 

 

 

 

 

 

MATERIAL

Hydraulic Excavator (Poclain/JCB/Mini Excavator) including Operator, Fuel & Machine Maintenance

0.0063

Day

8000

50.40

Hire and running charges of Hywa/Dumper.

0.0063

Day

1700

10.71

Total Material

 

 

 

61.11

 

 

LABOUR

Rock Excavator

0.0705

Day

329.00

23.19

Rock Breaker

0.159

Day

329.00

52.31

Rock Hole Driller

0.0355

Day

329

11.67

Beldar

0.05

Day

329

16.45

Male Helper

0.135

Day

329

44.41

Sundries

1.79

LS

1.78

3.19

Total Labour

 

 

 

151.22

 

 

Total Material & Labour

 

 

 

 

212.33

 

Overheads

Add 1% Water Charges

 

 

 

2.1233

 

 

 

TOTAL AMOUNT

 

 

 

214.45

 

 

15% Contractor

 

 

 

32.17

 

 

TOTAL AMOUNT

 

 

 

246.62


4. 
Excavation in Hard Rock. (BY Breaker)

Excavation work by Hydraulic excavator in foundation, trenches, drains up to 1.5m, including Excavated material shifting on Site

Sr. No.

Item Description

Quantity

Unit

Material/Labour Description

Constant

Unit

Rate

Amount

1

Excavation in Hard Rock. (BY Breaker)

 

 

1

Cum

 

 

 

 

 

 

MATERIAL

Hydraulic Excavator (Poclain/JCB/Mini Excavator) including Operator, Fuel & Machine Maintenance (By Breaker)

0.0063

Day

8000

50.40

Hire and running charges of Hywa /Dumper.

0.0063

Day

1700

10.71

Total Material

 

 

 

61.11

 

 

LABOUR

Rock Excavator

0.0855

Day

329.00

28.12

Rock Breaker

0.1765

Day

329.00

58.06

Rock Hole Driller

0.0530

Day

329.00

17.43

Beldar

0.050

Day

329.00

16.45

Male Helper

0.130

Day

329.00

42.77

Sundries

1.35

LS

1.78

2.40

Total Labour

 

 

 

165.23

 

 

Total Material & Labour

 

 

 

 

226.34

 

Overheads

Add 1% Water Charges

 

 

 

2.26

 

 

 

TOTAL AMOUNT

 

 

 

228.60

 

 

15% Contractor

 

 

 

34.29

 

 

TOTAL AMOUNT

 

 

 

262.89


5. 
Excavation in Hard Rock. (BY Breaker/Blasting)

Excavation work by Hydraulic excavator in foundation, trenches, drains up to 1.5m, including Excavated material shifting on Site. 

Sr. No.

Item Description

Quantity

Unit

Material/Labour Description

Constant

Unit

Rate

Amount

1

Excavation in Hard Rock. (BY Breaker/Blasting)

 

 

1

Cum

 

 

 

 

 

 

MATERIAL

Hydraulic Excavator (Poclain/JCB/Mini Excavator) including Operator, Fuel & Machine Maintenance (By Breaker)

0.0125

Day

8000

100.00

Hire and running charges of Hywa/Dumper.

0.0125

Day

1700

21.25

Total Material

 

 

 

121.25

 

 

LABOUR

Rock Excavator

0.124

Day

329.00

40.79

Rock Breaker

0.300

Day

329.00

98.70

Rock Hole Driller

0.1060

Day

329.00

34.87

Beldar

0.050

Day

329.00

16.45

Male Helper

0.130

Day

329.00

42.77

Blasting Powder

0.642

Kg

35

22.47

Blasting Fuse with Wire

0.7

Per Nos

15

10.50

Sundries

1.85

LS

1.78

3.35

Total Labour

 

 

 

269.90

 

 

Total Material & Labour

 

 

 

 

391.15

 

Overheads

Add 1% Water Charges

 

 

 

3.91

 

 

 

TOTAL AMOUNT

 

 

 

395.06

 

 

15% Contractor

 

 

 

59.25

 

 

TOTAL AMOUNT

 

 

 

454.32


6.
 Excavation in Hard Rock. (BY Breaker/Without Blasting)

Excavation work by Hydraulic excavator up to 1.5m, including Excavated material shifting on Site. 

The rate of shifting of material is considered on-site, but if there is no space to spread the excavated material so you need to shift all the excavated material to another place other than the site, the rate of shifting of excavated material depends on the distance between two sites.

Sr. No.

Item Description

Quantity

Unit

Material/Labour Description

Constant

Unit

Rate

Amount

1

Excavation in Hard Rock. (BY Breaker/without Blasting)

 

 

1

Cum

 

 

 

 

 

 

MATERIAL

Hydraulic Excavator (Poclain/JCB/Mini Excavator) including Operator, Fuel & Machine Maintenance (By Breaker)

0.0125

Day

8000

100.00

Hire and running charges of Hywa/Dumper.

0.0125

Day

1700

21.25

Total Material

 

 

 

121.25

 

 

LABOUR

Rock Excavator

0.265

Day

329.00

87.185

Rock Breaker

0.6175

Day

329.00

203.15

Stone Chiseller

0.1060

Day

363.00

38.47

Blacksmith 2nd Class

0.0175

Day

399.00

6.98

Beldar

0.075

Day

329.00

24.675

Male Helper

0.150

Day

329.00

49.35

Sundries

1.784

LS

1.78

3.175

Total Labour

 

 

 

412.98

 

 

Total Material & Labour

 

 

 

 

534.24

 

Overheads

Add 1% Water Charges

 

 

 

5.34

 

 

 

TOTAL AMOUNT

 

 

 

539.57

 

 

15% Contractor

 

 

 

80.93

 

 

TOTAL AMOUNT

 

 

 

620.50

 All above rate analysis are considered as per daily consumption and daily work is done of a machine and Labour, All rate are referred from Government approved agency, Rate of all machinery are varies from actual rate or Market rates, as well as rate, will vary as per the location of work. Also you can decide the rate of the item as per the work volume and specification of work.