Before learning each rate analysis we should know about the concrete rate analysis is fully dependent on the Mix design of concrete which should be certified from the authorized lab. in the last blogs, we have mentioned it. but now we are just reminding about it that mix design also depends on the location of the site, quality of material, density, and specific gravity of the material. everyone should aware it that all concrete rate analysis fully depends on the mix design, so please take proper knowledge about mix design, here we are given format about how to prepare rate analysis and how many cost you should consider while preparation of estimate of any project.
Now we are learning about M 30 concrete Manually.
M30 is generally using for Slab and Columns, thus is reach concrete having good strength and durability. It needs to add some admixtures to gain strength in stipulated time and it should be workable while concreting. sometimes we can found this grade concrete in Self Compacted Concrete (SCC). Self Compacted Concrete does not need to use Vibrator while concrete.
Material Required for M 30 Concrete.
Cement OPC 53 Grade
Crush Sand
Coarse Aggregate 10mm
Coarse Aggregate 20mm
Concrete Admixture
Potable Water
In the Above Image, we are given the format of M30 Concrete for Manual Making on-site. but you should be very careful while it is making on-site because the Concrete making process depends on its weight. if you are not aware of the weight of mixing raw material, you can't get the desired strength of given concrete grade.
Rate Analysis of M30 Ready-mix Concrete.
Mix design and weight is set on the Plant software. almost all the concrete plants are fully Computerized therefore the weight of raw material is correct and the mixing process is very good than out site manual mixer.
In the above format, we have given the format of M30 Concrete Ready Mix, but while preparing the actual rate analysis you should visit your site location and then visit the around raw material supplier's as well as nearby concrete plant. then you can get the actual cost of material and labor and after getting all the details from the site location you can easily prepare a rate estimate and which will be very cost effective.
If you require any format in excel with fully ready format with formulas, then mail on director.cbec@gmail.com
Team
CBEC India
5 Comments
thank you for your interesting infomation. concrete houston
ReplyDeleteAwesome blog. I enjoyed reading your articles. This is truly a great read for me. I have bookmarked it and I am looking forward to reading new articles. Keep up the good work! St Louis concrete contractors
ReplyDeleteThis comment has been removed by a blog administrator.
ReplyDeleteI might want to thank you for the endeavors you have made recorded as a hard copy this article. I am trusting a similar best work from you later on also. Truth be told your exploratory writing capacities has motivated me to begin my very own BlogEngine blog now. Extremely the blogging is spreading its wings quickly. Your review is a fine case of it. concrete staining
ReplyDeleteThis comment has been removed by a blog administrator.
ReplyDelete