BACKFILLING WORK
1. Name of
Work & Description
Backfilling Work is required to fill the excavated area of the foundation of the building or any structure from a hard surface.
Sometimes we need to do more backfilling more than ground level due to increase
the height of plinth level, on infrastructure field backfilling, is most
important part because the top level of road and highways is calculated as per
nearest dams or nearest river HFL (Highest Flood Level).
Before excavation work, we need to find out the
material quality of backfilling work. With some laboratory tests and physical
tests.
Types of using of Material for Backfilling Work.
1 Soft Soil
2 Murum (Same Gravels)
3 Murum (Brown Stone Color uniform size)
4 Murum (60-100mm size)
5 Boulders
6 Debris
2. IS Code No.
IS Code For Excavation &
Backfilling Work Code of Safety: IS 3764-1992
There is No Specific Code
for Backfilling
3. The Drawing Needs to Read.
Backfilling work is need
to do after building the foundation completed or after top level of structure final.
Following drawing need to
read before Backfilling work, or before starting to backfilling.
1 Building
Foundation Plan
2 Bridge
Foundation Plan
3 Plinth
Section
4 Reduced
Level Plan
5 Plot
Layout Drawing
6 Road
Level
7. Road
Section
8.
Foundation Sectional Drawing
4. Location of Work
Backfilling can be done with the following Locations.
1 Building Foundation
2 Podium Foundation
3 Basement
4 Under Ground Water Tanks
5 Bridge Foundation
6 Culvert
7 Dam
8 Trench
9 Road
5. Standard Procedure of Work (Step by Step)
Work Procedure before Start the Backfilling
1 Read Plot Layout Drawing Carefully.
2
Calculate Approximate measurement to get the idea of required backfill material.
3 Read
Foundation drawing plan, where Footing and Raft of the building are outside then
building lines.
4 Calculate
Outer to outer distance from foundation drawing of building or bridge
structure.
5 Do site
visit of Backfill material quarry. Please keep quarry distance nearest form
your site.
6
Finalize material as per your requirement.
7
Finalize the rate as per your budgeted amount for backfilling work.
Work Procedure
during the Backfilling
1 Remove
all the Material from Pit, or Backfilling Area.
2 Fill
loose material with help of machine up to 300mm height.
3 Do not backfill murum more than 300mm.
4 Do not allow boulders in Backfill murum.
5 Do not allow any vegetation/twigs
6 Do not allow keep the boulders near RCC
structure, it can be damaged RCC member.
7 Backfilling must be done by first filling
the excavated soils in layers of 300–500mm and tamping it with a vibrator. Till the desired level. The soil is moistened up to the optimum moisture content to
establish optimum compaction and best results.
8 Barricade
the area backfilling area when machinery is working.
9 Check
and Note down backfilled area levels with help of Auto level by the same interval
as you have done during taking an actual ground level reading.
6. Checkpoints
1 Check Machine Capacity as well as which type of machine is Required.
2 Instruct
to machine operator regarding the depth of Backfilling Material as well as the thickness of each layer.
3 Instruct
to Operator to compact each layer properly.
4 Compact
each layer of the earth not exceeding 200mm.
5 Earth/soil should be free of
vegetation/twigs if any.
6 Earth/soil should be free of boulders if
any.
7 Rolling should be done with a 5-ton mechanical
roller after sprinkling enough water and core cutter samples taken for every
150sq.m
8 Proceed to the next layer after achieving a minimum
of 95 % of MDD(maximum dry density).
9 Keep
all workers Safe distance from Machine.
10 Back the filling must be done by first filling the excavated soils in layers of 30–50 mm
and tamping it with a vibrator. Till the desired level. The soil is moistened up to
the optimum moisture content to establish optimum compaction and best results.
11 After completion
of compaction arrange the architect visit to inspect the level as per Sections.
Check the
Plinth Level and desired level before complete the backfilling, also keep down
the level of backfilling area for Soling, PCC & Flooring, or for Road work
keep the level down for WBM, Tack Coat, Seal Coat Etc.
12 Please
check Depth of Soling, PCC, Footing/Raft, and Plinth Beam before complete the
excavation.
For
Example: If Plinth Level is Given 1.0m
Above GL.
Then Calculate
Minimum Backfilling Depth
Soling for Footing:
0.23m
PCC for Footing: 0.15m
Tiling Work : 0.050m
Then Top Level of
Compacted Backfilling Area is 0.57m below from Plinth Level.
7. Equipment and Machinery
There are two types of Backfilling
is done
Manual Backfilling
Manual Backfilling
can be done with the worker by using hand tools like shovels, etc. and 250-1000kg The compactor can be used for Compaction, Generally manual backfilling must be done
at the not accessible area for big machines like at Parking, Under the Building, at
Basement, Under the bridge, etc. but for mass Backfilling can not be possible by
manually. It will be too costly and time consumable.
Mechanical Backfilling.
With the help of advance technology excavation is made too much easy and cost-effective
as well as time-saving.
Following The machine is using for excavation
1 Backhoe Loader (JCB)
2 Excavator (Poklain)
3 Mini Excavator (Mini poclain, Bob-Cat)
4 Mini Compactor
5 Plate Compactor
6 Road Roller
7 Grader
8 Vibro Roller
9 Hywa : For murum Shifting
10 Dumper: For murum shifting
11 Tractor: For murum shifting
12 Water Tanker
13 Dozer
8. Measurement and Quantity Survey
For Calculation of backfilling
area and quantity of backfilled material we need the following points.
1 Excavated ground Level Reading: Average Level
of each interval.
2 Backfilled
Ground Level Reading: Average level of each interval.
3 Actual backfilled
Area: Prepare geometrical shapes as per level interval as we can find exact backfilled the area as well as the depth of backfilling.
Depth of Backfilling
= RL of excavated GL – RL of backfilled GL
Quantity
of Backfilled Area = Actual backfilled Area X Depth of Backfilling
Please prepare the chart as per the Excavation work Session.
9. Checklist
Backfilling Work Checkpoints
1 Mark Exact area of Backfilling
2 Keep RCC
Structure, Pipe Line, Chambers, Electrical Wire, etc. Safe
3 Compact
up to 95 % of MDD(maximum dry density).
4 Use
Vibro Roller as per your requirement.
5 Barricading
is done when machines are working.
6 Keep
exact 300mm Layers to compaction.
7 Heavy equipment, such as backfilling
machinery and road traffic shall be kept back from the excavated sides at a
distance not less than the depth of backfilling or at least 6 m for area deeper
then 6 m.
8 The use of power shovels or draglines in
a trench, because of his violent thrust or blows delivered, rapidly renders the
banks of the trench unstable and dangerous to people working nearby. These
conditions shall be watched for and suitably remedied or eliminated.
9 Pathways shall be non-slippery and shall
be of adequate width of not less than 75 cm. They shall be strong enough to
withstand the intended use.
10 Backfilling areas shall be adequately
lighted for night work.
10. On-site Experience
Readers
Experience: At an MNC
Project the work order is for industrial plant shed and area of the shed is
approximate 30000 Sqft, but movable area and road this plant plinth area is
approximate 72000Sqft and height are approximately 7m from the existing ground level.
Total work completion time is given by the client is 6 months including Monsoon
season. And the site location is in the hilly area. But our bad luck is after cutting
of grass and murum backfilling completed up to 2 meters, rain is started, and
continuously falling up to more than 40 days. And for dry this area again give
40 days. But when we have to restart the work, the murum is not as much dry as
we think, at that site we did a lot of work on it, we removed 2 layers of that murum and refill it. Obviously, the client gives us 90 days extra as well as they understood the
exact situation of work.
Mr. Ashok (Sr. Supervisor)
Team
CBEC INDIA
6 Comments
This comment has been removed by a blog administrator.
ReplyDeleteTrench boxes Very efficiently written information. It will be beneficial to anybody who utilizes it, including me. Keep up the good work. For sure i will check out more posts. This site seems to get a good amount of visitors.
ReplyDeleteThis comment has been removed by a blog administrator.
ReplyDeleteThis comment has been removed by a blog administrator.
ReplyDeleteThis comment has been removed by a blog administrator.
ReplyDeleteThis comment has been removed by a blog administrator.
ReplyDelete