Rate Analysis of PCC
(Plain Cement Concrete)
This is used at below any foundation to make a clean and level
surface for easy to work, away from sand, dust, mud, etc. This is the temporary structure created to ease your work. PCC is not a Structural Member which can
bear any load or pressure. But this plays a very important role when foundation
work is going on. PCC will help to keep it as per measurement and as per
design.
Sometimes
the natural ground has too much uneven surface, in those situations, there is
doing Plum concrete. That means 60% of Natural Hard Stone and 40% of Plain Cement
concrete will fill with doing some shuttering work to control Size. This will
help to create a plain Surface to ease the work.
General Use of Plain Cement Concrete (PCC)
1.
Below Footing
2.
Below Raft
3.
Below Concrete Road
4.
Below Grade Slab
5.
Below Box type Waterproofing
6. At
Labour Camp
7.
Work Station of Labour Like Steelyard, Cutting yard, etc.
8. In
Godown or Store Room.
9. In
Site office.
10.
In Plum Concrete at uneven Surface.
In
above location, PCC can be done at Normally to work easily.
but
What about Plum Concrete Work. Plum Concrete is used at Uneven surfaces to Fill
it by Plum Concrete of 60% of Rubble and 40% of Plain Cement Concrete.
sometimes
plum concrete can be used at Low bearing capacity soil, but This should be used
for small structure not for Building, tower or any big structure because Plum
concrete is also not a structural member who can bear load and pressure.
Here
we have given some example of Rate analysis of Plum Concrete and Plain Cement
concrete (PCC).
Rate Considered: (All Rate is
Basic Rate Taxes and Transportation to consider extra)
Cement:
Rs. 265.00/Bag
Crush
Sand: Rs. 1095.00/cum i.e. Rs. 3100/Brass
Course
Aggregate 10mm: Rs. 953.00/cum i.e. Rs. 2700/Brass
Course
Aggregate 20mm: Rs. 953.00/cum i.e. Rs. 2700/Brass
Fly
Ash: Rs. 2.00/Kg
Admixture:
Rs. 48/Liter up to M25 or Rs. 66/Liter above M30
Labour: Rs. 805/Cum
Extra
Overheads: Rs.950/Cum (This cost considered Including Transportation, Shifting,
Water Electricity, Housekeeping, PF/ESIC.Etc.)
In
General Condition Lot of builders and Subcontractors are sublating this work on
Sqft basis or Per Bag basis to Subcontractor or Concrete gang Who can do it on
PCC Rs. 6.00/ Sqft and Plum Concrete in 8.50 to 9.00 Rs. Per Cuft that is 300
Per Cum
PLUM CONCRETE (60:40)Ratio
Quantity
: 1.00 Cum
Material
|
Labour
|
||||||||||
Material
|
Unit
|
Constant
|
Rate
|
Amount
|
Total Amount
|
Labour
|
Unit
|
Quantity
|
Rate
|
Amount
|
Total Amount
|
Cement
|
Bags
|
1.15
|
265
|
305.70
|
1311.50
|
Labour work for
RCC
|
Cum
|
1.00
|
450.00
|
450.00
|
981.60
|
Crush Sand
|
Cum
|
0.20
|
1,095
|
216.68
|
Material
handling charges
|
0.5%
|
6.56
|
||||
Course
Aggregate 10- 12 mm
|
Cum
|
0.10
|
953
|
99.08
|
Overheads
|
Cum
|
1.00
|
525.00
|
525.00
|
||
Course
Aggregate 20
-25 mm
|
Cum
|
0.25
|
953
|
236.12
|
|||||||
Fly ash
|
Kg
|
33.60
|
2
|
50.40
|
|||||||
Rubble
|
Cum
|
0.60
|
673
|
403.54
|
TOTAL
RATE: Rs. 2293.10/Cum Say Rs.2294.00/Cum
(Shuttering Cost is Extra)
Rate And Material Analysis of PCC: Plain Cement Concrete
PCC 05 (1:4:8)
Quantity:
1.00 Cum
Material
|
Labour
|
||||||||||
Material
|
Unit
|
Constant
|
Rate
|
Amount
|
Total Amount
|
Labour
|
Unit
|
Quantity
|
Rate
|
Amount
|
Total Amount
|
Cement
|
Bags
|
2.06
|
265
|
545.90
|
2208.51
|
Labour work for
RCC
|
Cum
|
1.00
|
805.0847
|
805.08
|
1,766.1
|
Crush Sand
|
Cum
|
0.67
|
1,095
|
729.82
|
Material
handling charges
|
0.5%
|
11.04
|
||||
Course
Aggregate 10- 12 mm
|
Cum
|
0.31
|
953
|
297.74
|
Overheads
|
Cum
|
1.00
|
950.00
|
950.00
|
||
Aggregate 20
-25 mm
|
Cum
|
0.47
|
953
|
451.44
|
|||||||
Fly ash
|
Kg
|
84.00
|
2
|
126.00
|
|||||||
Admixture up to
M30
|
Kg
|
1.20
|
48
|
57.60
|
TOTAL
RATE: Rs. 3974.60/Cum Say Rs. 3975.00/Cum
(Shuttering Cost is Extra)
PCC M10 (1:3:6)
Quantity:
1.00 Cum
Material
|
Labour
|
||||||||||
Material
|
Unit
|
Constant
|
Rate
|
Amount
|
Total Amount
|
Labour
|
Unit
|
Quantity
|
Rate
|
Amount
|
Total Amount
|
Cement
|
Bags
|
2.88
|
265
|
764.26
|
2327.54
|
Labour work for
RCC
|
Cum
|
1.00
|
805.0847
|
805.08
|
1,766.7
|
Crush Sand
|
Cum
|
0.49
|
1,095
|
541.70
|
Material
handling charges
|
0.5%
|
11.64
|
||||
Course
Aggregate 10- 12 mm
|
Cum
|
0.26
|
953
|
247.69
|
Overheads
|
Cum
|
1.00
|
950.00
|
950.00
|
||
Course
Aggregate 20 -25 mm
|
Cum
|
0.62
|
953
|
590.29
|
|||||||
Fly ash
|
Kg
|
84.00
|
2
|
126.00
|
|||||||
Admixture up to
M30
|
Kg
|
1.20
|
48
|
57.60
|
TOTAL
RATE: 4094.30 Say Rs. 4095.00/Cum
(Shuttering Cost is Extra)
PCC M15 (1:2:4)
Quantity
: 1.00Cum
Material
|
Labour
|
||||||||||
Material
|
Unit
|
Constant
|
Rate
|
Amount
|
Total Amount
|
Labour
|
Unit
|
Quantity
|
Rate
|
Amount
|
Total Amount
|
Cement
|
Bags
|
4.94
|
265
|
1,310.16
|
2967.24
|
Labour work for
RCC
|
Cum
|
1.00
|
805.0847
|
805.08
|
1,769.9
|
Crush Sand
|
Cum
|
0.58
|
1,095
|
631.73
|
Material
handling charges
|
0.5%
|
14.84
|
||||
Course
Aggregate 10- 12 mm
|
Cum
|
0.34
|
953
|
325.98
|
Overheads
|
Cum
|
1.00
|
950.00
|
950.00
|
||
Course
Aggregate 20 -25 mm
|
Cum
|
0.56
|
953
|
531.52
|
|||||||
Fly ash
|
Kg
|
73.50
|
2
|
110.25
|
|||||||
Admixture up to
M30
|
Kg
|
1.20
|
48
|
57.60
|
TOTAL
RATE: 4737.20 Say Rs. 4740.00/Cum
(Shuttering Cost is Extra)
In above analysis, We have Considered the Material Density as Follows.
1.
Cruah Sand : 1600 Kg/Cum
2.
10mm Metal : 1560Kg/Cum
3.
20mm Metal: 1550kg/Cum
All
the Details are given in mix design report which is prepared for your site and the mix design depends on quarry material. Material Density can be changed as per
Quarry location and Material quality, as well as Cement content, can be changed as
per quarry Material quality.
Generally A lot of Builders, contractors are using thumb rule when doing PCC work.
General The market rate of PCC work.
PCC
with Material: Rs. 3500-4000/Cum
PCC
only Labour: Rs.400/Cum
100
to 150mm thick PCC only Labour: Rs.6.00/Sqft
Plum
Concrete Only Labour: Rs.8.50-9.00/Cuft That is 300/Cum
Cement
Bag: Rs.50- 60/Bag.
Shuttering
With Material: Rs.450-550/ Sqm
All
above Rates is current market rate and analysis are considered as per Mix
design report. Which is Change as per the location and Mix Design Report,
you can refer the format and
can try preparing your site analysis as per your site mix design.
If you need its soft copy in excel format with formula please mail us on director.cbec@gmail.com
Team
CBEC India
16 Comments
This comment has been removed by a blog administrator.
ReplyDeleteThanks for sharing the best information and suggestions, I love your content, and they are very nice and very useful to us. If you are looking for the best Driveway Resurfacing Sydney, then visit Sydney Wide Spray Pave. I appreciate the work you have put into this.
ReplyDeleteThank you for your observation, If possible please shear your profile.
DeleteWe read your blog , share most useful information in blog .
ReplyDeleteBest Waterproofing Melbourne
Most usefull information
ReplyDeleteThank you for your observation
DeleteSo how would you be able to deal with develop your neighborhood construction organization on the web? túlméretes szállÃtás Europa-Road Kft.
ReplyDeleteSend your Requirement on director.cbec@gmail.com
DeleteAs you look for the best shampoo detox product for you, look through the instructions to see how long it takes to apply the product. One of the first things people do when buying a new product is assessing the reputation of the brand behind it. Detox shampoos should be no different. The brand reputation gives you an idea of the safety, efficiency, and long-term effects of using the product. If it’s boiling, then you’ve gone too far. The ideal time would be no more than 10 seconds in the microwave. Visit: https://www.urineworld.com/
ReplyDeleteNice Post i Like it, For more interesting knowledge about Civil Engineering visit:The Civil Engineering
ReplyDeleteI was looking for parts washing station. Can anybody tell me where could I get this service at a reasonable price? Me and one of my friends need this service.
ReplyDelete
ReplyDeleteIt was such a good post. Visit stainless steel 304 seamless pipe suppliers. Thanks for sharing.
This comment has been removed by a blog administrator.
ReplyDeleteThis comment has been removed by a blog administrator.
ReplyDeleteThis comment has been removed by a blog administrator.
ReplyDeleteThis comment has been removed by a blog administrator.
ReplyDelete